Step 1: Size for the load you have, not the load you want
-
Step 2: Pick the fuel, then read the BTU numbers
-
Step 3: Check the location and the permit before the unit ships
-
Step 4: Compare quotes on what's included, not what's quoted
-
Step 5: Add the accessories the unit actually needs
-
Step 6: Build a maintenance list and cross-reference the parts
-
What I still see go wrong
Three years ago, I signed off on what looked like a clean 22kW standby generator order for a customer in Sandpoint, Idaho. The unit arrived in six weeks. Eight months later it wouldn't carry the load because the gas line was undersized. Cost to fix: about $2,400 in repipe and re-inspection, plus two very cold days for the customer.
That's the day I started keeping a checklist. I handle standby generator orders for a dealer network, and I've personally documented enough mistakes — somewhere north of $4,300 worth — to have a strong opinion about what goes wrong and in what order.
Here's the six-step version I use now. It's caught 47 potential errors in the past 18 months. It works for commercial and residential standby units, and most of it applies to portable generators too. If you're buying, quoting, or installing, run the list in order. Skip a step and you'll pay for it later — usually in dollars, sometimes in cold customers.
Step 1: Size for the load you have, not the load you want
This is where I lost my first $1,100. A homeowner wanted a Generac generator sized for "everything," so I quoted a 22kW. Fine unit. Also oversized by about 4kW, which meant a bigger unit, a bigger gas line, and a bigger pad — none of which he needed.
Here's what actually goes into sizing:
- Running watts for everything you want on the circuit — furnace blower, well pump, fridge, freezer, sump, lights, one or two outlets for medical devices.
- Starting watts for the motors. A 1/2 HP well pump can draw 3x its running load for a second. An A/C compressor is worse.
- What you're willing to leave off. Almost nobody needs the range, the dryer, and the hot tub at the same time. Deciding this before sizing saves 4–6kW of capacity and thousands of dollars.
The 26kW isn't automatically better than the 22kW. It's better only if your calculated load actually needs the headroom. Use Generac's own sizing tool, or do the arithmetic on paper — but do it before you quote. Trust me on this one.
Step 2: Pick the fuel, then read the BTU numbers
Here's the step most people skip. They pick natural gas because it's already at the house, then they're surprised when a 26kW unit starves under load.
Two numbers matter:
- Natural gas: roughly 1,000 BTU per cubic foot (Source: U.S. Energy Information Administration heat content tables; your utility's actual value varies).
- Propane: roughly 2,516 BTU per cubic foot as a vapor (Source: Propane Education & Research Council conversion data).
The generac 26kw generator btu rating pdf lives in the spec sheet on Generac's site, and it also lists the required fuel pressure — typically 3.5 to 7 inches of water column for natural gas, 10 to 12 for propane. If the gas pipe can't deliver that at full load, the unit will run, stumble, and eventually throw a fault.
What I do now: measure the gas run in feet, look up the required CFH for the unit, and size the pipe against the gas supplier's table. A 3/4-inch line that's fine at 15 feet is not fine at 40 feet. That single table saved me two warranty calls in 2023.
Step 3: Check the location and the permit before the unit ships
This is the step that gets ignored when everyone's excited about the equipment quote.
Clearance requirements (from NFPA 37 and most local codes):
- 5 feet from the building wall, unless the manufacturer's manual allows less.
- 5 feet from any operable window, door, or fresh-air intake.
- Clear of the gas meter and any vent termination.
- Enough space above and in front for service access.
For Sandpoint, Idaho specifically, that's the city's building department permit plus the county electrical inspection, and the gas line change usually triggers its own permit. Three permits. If you quote a job without confirming which ones apply, you'll eat the fees.
Also: if there's an HOA, ask for the approval letter in writing before you order the unit. I've seen a $9,200 order sit in a driveway for six weeks while the board debated a fence height. Don't be that order.
Step 4: Compare quotes on what's included, not what's quoted
I've learned to ask what's NOT included before I ask what's the price.
Here's the $1,800 lesson: I once accepted what looked like the lowest bid on a 22kW install. The number didn't mention the concrete pad ($340), the gas line upsizing ($910), the electrical permit ($180), or the startup battery ($140). By the time the work was done, the "cheapest" quote was $1,570 more than the middle one.
Run every quote against this list before you compare totals:
- Unit and transfer switch, both included and itemized?
- Pad, gravel, or concrete — who's pouring it?
- Gas line: existing or upsized? Cost of the run per foot?
- Electrical: permits, conduit, panel work, load calculation?
- Startup battery and battery charger, included or not?
- Labor: same-day or scheduled two weeks out?
- Warranty terms in writing?
The vendor who lists all the fees upfront — even if the total looks higher — usually costs less in the end. Prices here are for general reference; verify current rates in your area.
Step 5: Add the accessories the unit actually needs
Two accessories get skipped on roughly a third of the jobs I see, and both show up later as service calls.
Surge protection. If you're protecting the transfer switch and the panel, you need a whole-home surge protector with a real joule rating. What are joules in a surge protector? The joule rating is how much energy the device can absorb before it stops protecting — 1,400 to 4,000 J is the typical whole-home range. Look for UL 1449 listing, a clamping voltage under 400 V, and a response time in nanoseconds. A $40 power strip won't do this job.
Battery maintenance. The starting battery is the single most common service call on a standby generator that otherwise runs perfectly. If the unit sits for months without exercising properly, the battery sulfates and loses capacity. A trickle or smart charger keeps it alive — an Enersys battery charger or an equivalent smart maintainer is worth the $80. Check that the charger matches the battery chemistry (AGM vs. flooded) before you plug it in.
Step 6: Build a maintenance list and cross-reference the parts
Once the unit is running, the job flips from installation to upkeep. This is where the checklist habit pays off again — and where a little cross-referencing saves real money.
The same logic people use for a toro timecutter oil filter cross reference applies to your generator: the OEM part number is one path, and aftermarket equivalents are another, but the gasket, thread pitch, and bypass pressure have to match or you're risking the engine. For a Generac air-cooled unit, that means the oil filter, air filter, spark plug, and fuel filter all have OEM numbers that cross to specific aftermarket equivalents — and a handful of them don't cross cleanly.
What I keep on the maintenance sheet:
- Oil and filter — every 100 hours or annually, whichever comes first.
- Air filter — every 100 hours, or every 50 in dusty conditions.
- Spark plugs — annual.
- Battery load test — every six months.
- Exercise cycle — weekly, and confirm it actually ran. "It's supposed to run" is not the same as "it ran."
One more thing: log every service call in the same place. I have a spreadsheet with 47 entries and every one of them traces back to a step in this checklist. That's not a coincidence.
What I still see go wrong
The same three failures show up again and again, no matter how many times I update the list:
Skipping the load calculation because the customer "knows what they want." They usually don't — they know what they're afraid of. Sizing answers the fear; guessing at the unit size doesn't.
Assuming the existing gas line is enough. It rarely is on a 22kW+ unit, and it's the most expensive thing to fix after the concrete is poured.
Comparing quotes on the top-line number only. If I had a dollar for every "cheapest" quote that turned into a change order, I'd have covered the $4,300 a long time ago.
The list isn't perfect. But it's honest, it's built from mistakes I actually made, and it's the one I'd hand to anyone buying a Generac generator — in Sandpoint, Idaho or anywhere else. Prices and code references are current as of January 2025; verify local rates and permitting before you order.